A task is one piece of close work in one period, such as a reconciliation, an accrual or an upload. A recurring task has its own copy, with its own files and history, in each period.

FieldMeaning
PreparersDo the work. Any one of them can act.
ReviewersApprove or return the work. Any one of them can act.
Second reviewersOptional; approve after the first reviewer.
Preparer DueWhen preparation is due.
Reviewer DueWhen review is due.
TaskSteps
Reviewed untickedPrepare, then done. No review.
JE CreationPrepare, review, then book the journal entry and have it signed off. Always reviewed.
All othersPrepare, then review.

Naming a second reviewer adds a second review.

Whether a task is reviewed is set by Reviewed on its template, and applies to the template’s open tasks. A task with no template has its own Reviewed box, under Type on its Configuration tab. Untick it for work that is reviewed on its reconciliation instead, such as a roll-forward that only builds the reconciliation’s support.

StatusMeaningWho acts next
Not StartedNot begun.Preparer
In ProgressBeing prepared.Preparer
In ReviewSubmitted to the reviewer.Reviewer
Needs ChangesReturned with a comment.Preparer
Second ReviewApproved by the first reviewer.Second reviewer
Ready for JEApproved; the journal entry isn’t booked.Preparer
JE In ProgressThe entry is being booked.Preparer
JE ReviewThe entry is booked, awaiting sign-off.Whoever gave final approval (the second reviewer, if there is one)
DoneComplete.—
BlockedSet by hand, with what it is waiting on.Preparer
N/ANot needed this month. Set while the month is in Setup; once the close has started, with Override status…, or the task is archived.—

The strip at the top of the Timeline shows the stages a task goes through, who owns each, and where it is.

The stage strip on a task's timeline

With the Prepare tasks permission, mark a task Blocked from Not Started or In Progress, with what it is waiting on. With Override status, Override status… blocks it from any other status but Done. Unblock returns it to Not Started if it was blocked from there, and to In Progress otherwise. A task blocked from Not Started is edited as a Not Started task is: its configuration saves as you change it, and moving a due date needs no reason.

The deliverable is the finished work the reviewer signs off; source files are what it was prepared from. Files that recur every month are file templates: each has its own row, and a task can’t be submitted until each document it produces is attached.

A task can wait on other tasks. Until each is Done or N/A, the task page shows Waiting on with the unfinished tasks, and the task’s status doesn’t change. This is different from the Blocked status, which someone sets by hand.

To add one, pick the task under Depends on in the task’s Configuration tab (on a task under way, click Unlock to edit first), or click the task’s Dependencies cell in the list. This takes the Change task type and dependencies permission.